Omexom concludes the building works for modernizing Substation 06 for CEB Distribuição

In March 2017, Omexom successfully concluded the commissioning of 138/13.8 kV, 64MVA SUBSTATION 06 for Companhia de Eletricidade de Brasília (CEB).

It was a turnkey solution for the endeavor. This included the project, the engineering, the total supply of equipment and systems, civil construction and electromechanical assembly – this substation being the second delivered by Omexom in Brasilia including GIS technology. The first one was for the SE (Substation) Estádio Nacional, and they both constitute the only SF6 Gas-Insulated Substations (GIS) installed in Brazil’s center-west region.

The new CEB substation will guarantee a quality, reliable power supply to the system and benefit users in the region.

.